Implementation Plan
To implement using the LS Central Implementation Guide, the system must be configured, and users are trained on data configuration and core processes as well as project management tasks.
Note: All timelines are assumed using the standardized chart of accounts included in the preconfigured data packages. If a custom chart of accounts is required, the timelines will increase due to the necessary training and configuration.
The estimated hours are intended for informational purposes only and meant to give you an overview on tasks and assist you to estimate a project.
| Area | On-Premises hours | LS Central SaaS Online Model hours | LS Central SaaS Hybrid Model hours |
|---|---|---|---|
| Project Management | 20 | 20 | 20 |
| Project Planning | 8 | 8 | 8 |
| Status Calls | 12 | 12 | 12 |
| Infrastructure | 32 | 8 | 32 |
| Data configuration and setup | 36 | 36 | 36 |
| System | 16 | 16 | 16 |
| Finance | 4 | 4 | 4 |
| Procurement | 12 | 12 | 12 |
| Retail | 4 | 4 | 4 |
| Replication | 8 | - | 8 |
| Key User Training | 40 | 40 | 40 |
| Additional user assistance | 16 | 16 | 16 |
| Project Close | 4 | 4 | 4 |
| Total | 156 | 124 | 156 |