Implementation Plan

To implement using the LS Central Implementation Guide, the system must be configured, and users are trained on data configuration and core processes as well as project management tasks.

Note: All timelines are assumed using the standardized chart of accounts included in the preconfigured data packages. If a custom chart of accounts is required, the timelines will increase due to the necessary training and configuration.

The estimated hours are intended for informational purposes only and meant to give you an overview on tasks and assist you to estimate a project.

Area On-Premises hours LS Central SaaS Online Model hours LS Central SaaS Hybrid Model hours
Project Management 20 20 20
Project Planning 8 8 8
Status Calls 12 12 12
Infrastructure 32 8 32
Data configuration and setup 36 36 36
System 16 16 16
Finance 4 4 4
Procurement 12 12 12
Retail 4 4 4
Replication 8 - 8
Key User Training 40 40 40
Additional user assistance 16 16 16
Project Close 4 4 4
Total 156 124 156